The Panasonic Plant in De Soto: Jobs, Hiring & Commute
A dated timeline of the plant, how hiring and training work, what Kansas promised in incentives, and the roads you will drive to get there.
Panasonic announced the De Soto plant on July 13, 2022, broke ground that November and opened it on July 14, 2025 with about 1,000 people hired. By June 2026 it employed about 1,800 and ran four production lines, with a second wing under construction. Jobs are posted on Panasonic Energy’s Kansas careers site, and apprenticeships run with JCCC and KCKCC. The State of Kansas estimated its APEX incentive package at $829.2 million. Drivers reach the plant from K-10 at Lexington Avenue via a rebuilt four-lane W. 103rd Street.
Timeline
How has the plant grown since it was announced?
From farm-field announcement in 2022 to four running lines in 2026.
| Date | What happened | Source |
|---|---|---|
| July 13, 2022 | Project announced: about $4 billion, up to 4,000 jobs | KS Commerce |
| Nov 2, 2022 | Groundbreaking | KS Commerce |
| Mar 20, 2024 | Supplier H&T Recharge announces a $110 million battery-can plant in De Soto with 180 jobs | KS Commerce |
| Q4 2024 | Panasonic begins using about 510,000 sq ft at Flint Commerce Center in De Soto | KS Commerce brief |
| July 14, 2025 | Grand opening and start of mass production; about 1,000 hired | KS Commerce |
| Feb 3, 2026 | About 1,400 employees; two lines running, two starting; second wing under construction with two lines expected in 2027 | Kansas Reflector |
| June 2026 | About 1,800 employees and four lines; plan to add data center energy-storage cells around 2028-2029 | KCUR |
News reports are dated; we found no newer headcount than June 2026. Checked Nov 20, 2026.
What has not been updated publicly: whether the 4,000-job target or the 2027 timing for the second wing has changed. Panasonic said in June 2026 that EV production will follow customer demand.
Hiring
How does hiring at Panasonic De Soto work?
Online applications, a talent-community alert list, and apprenticeships with two community colleges.
- Where to apply: Panasonic Energy Kansas careers, which groups jobs into Engineering & Technical, Manufacturing & Maintenance, Administrative & Support, and Quality & Safety.
- Johnson County Community College partnered on an apprenticeship that includes an 8-week training simulation (KSHB, Feb 2025).
- Kansas City Kansas Community College runs a 16-credit-hour operator registered apprenticeship for the plant that had served 120-plus students by January 2026 (KCKCC).
- Job fairs: a February 2026 fair targeted skilled machine technicians with manufacturing experience and included an on-site drug test (Johnson County Post).
Pay and benefits come from the employer, not from us; ask the recruiter. We will happily help with the other big number in your life, the one on the house.
Incentives
What incentives did Kansas give Panasonic?
The state estimated the APEX package at $829.2 million, paid as the company invests and hires.
| Piece | Estimated amount |
|---|---|
| Investment tax credit (12.5% over 5 years) | $500 million |
| Payroll rebate (10% over 10 years) | $234 million |
| Training and education | $5 million a year for 5 years |
| Relocation | $1 million a year for 10 years |
| Sales tax exemption | $60.2 million over 5 years |
| Total estimate | $829.2 million |
Source: Kansas Department of Commerce, Checked Nov 20, 2026. The Kansas City Star reported in 2022 that the agreement itself sets investment, opening and operating terms rather than a required job count.
Roads
Which roads lead to the plant, and what is changing?
The local roads were rebuilt in 2024; the big K-10 widening is approved on paper but not funded.
| Project | Status | Source |
|---|---|---|
| W. 103rd St. (Evening Star Rd to Lexington Ave/K-10) and Astra Pkwy rebuilt as four-lane divided roads with sidewalks, bike lanes and lighting | Finished 2024 | KDOT |
| K-10 at Lexington Ave interchange loops widened, new signals | Done 2024 | Johnson County Post |
| K-10 Corridor Capacity Improvements: 16.5 miles, county line to I-435, about $1.16 billion | Federal approval June 2025; not funded for construction; no schedule | KDOT |
| Interchange lighting at K-10/Kill Creek and K-10/Cedar Creek | Let to contract Dec 2025 | KDOT |
Transit: RideJoCo microtransit runs weekdays 6 a.m. to 8 p.m. ($5 for the first 5 miles plus $2 per extra mile as posted). We found no fixed bus route to the plant, so confirm coverage with Johnson County Transit.
Astra Park
What else is planned at Astra Enterprise Park?
Industry, solar, parks and data centers on more than 9,000 acres.
- The City of De Soto describes Astra as 9,000-plus acres planned for about 2,700 acres of parks and public benefit, 1,350 industrial, 3,000 utility-scale solar and 2,500 multi-use or light industrial, with cleanup to be complete by 2028 (City of De Soto).
- Digital Realty bought about 1,400 acres in May 2026; its Phase 1 data center was approved by the planning commission on Sept 22, 2026, and a resident petition seeks a public vote (Digital Realty; KSHB).
- Housing has been discussed for parts of the old ammunition plant land. The Army has said residential and industrial cleanup standards differ and groundwater will be monitored long term (Kansas City Magazine, May 2024). If you look at land near the site, ask for the environmental records.
We follow these projects month by month on Data Center Watch and KC Development Watch.
FAQ
Panasonic plant questions
When did the Panasonic De Soto plant open?
Panasonic held its grand opening and started mass production on July 14, 2025, about 32 months after the November 2, 2022 groundbreaking.
How many people work at the plant?
About 1,800 as of June 2026, up from about 1,000 at opening and 1,400 in February 2026. The announced target is up to 4,000 direct jobs.
Is the plant still hiring?
Openings continued in 2026, but Panasonic said in June 2026 it had no new hiring projections. Check the Panasonic Energy Kansas careers site for current postings.
Does Panasonic offer training or apprenticeships?
Yes. Apprenticeship paths run with Johnson County Community College (including an 8-week training simulation) and Kansas City Kansas Community College (a 16-credit-hour operator apprenticeship).
What does the plant make?
2170 cylindrical lithium-ion battery cells for electric vehicles. In June 2026 Panasonic said it will also make data center energy-storage cells starting around 2028 to 2029.
How much did Kansas pay in incentives?
The Kansas Department of Commerce estimated the APEX package at $829.2 million over up to 10 years, including tax credits, a payroll rebate and training money.
Is K-10 being widened?
A 16.5-mile K-10 widening plan received federal environmental approval in June 2025, but KDOT lists it as not currently funded for construction and has no schedule.
Are there other big projects next to the plant?
Yes. Data center campuses are planned or under construction at Astra Enterprise Park, along with solar and industrial land. We track them on our Data Center Watch page.
Starting at the plant soon?
We will map homes by drive time to Astra Parkway at your shift hours and help you decide between renting first and buying.
Wingman Real Estate – The Shopper Team · Brokered by REAL Broker, LLC · (913) 543-3332 · Angela@shopwithshopper.com · General information only, not legal, tax or lending advice; verify with the office or agency named. Not affiliated with or endorsed by any employer, military service or government agency named on this page. Information deemed reliable but not guaranteed. Equal Housing Opportunity.

Full-service real estate across the Kansas City metro, Lawrence and Topeka, on both the Kansas and Missouri sides.
(913) 543-3332
Angela@shopwithshopper.com
7300 W 110th St, Overland Park, KS 66210
Buy & Sell
Wingman Real Estate – The Shopper Team is a team of licensed real estate agents brokered by REAL Broker, LLC. Licensed in Kansas and Missouri. Equal Housing Opportunity. Information deemed reliable but not guaranteed. © 2026 Wingman Real Estate – The Shopper Team. Privacy Policy · Terms